When the screw feeder is applied on dosing and distributing , in order to feed materials evenly, prevent materials dropping down, screw feeder shall be installed horizontally. For example, if continuous feeding materials ,there can install below 10 degree . For the sticky material or wet materials ,the screw feeder can be installed below 15 degree. After the installation ,there shall leave a suitable clearance . The horizontal section shall be level, the hang device shall be connected softly. Before empty test, must check and tighten up all screw bolts ,especially the anchor bolts. When empty test running 3-5 hours ,shall tighten up all fasteners. When test with materials ,all motors shall rotate .For the vibrating ,two sets of vibrating motors shall rotate at the same time . Check the amplitude ,current and noise regularly. If any abnormal ,shall stop immediately. Add lubrication on bearings every 2 months. In the high temperature ,shall add lubrication every month.